YOU CAN SKIP THIS PART(short joke)...SCROLL DOWN FOR NEWS BELOW
A young couple moved into a new neighbourhood. The next morning while eating breakfast, the young woman saw her neighbour through the window hanging the wash outside.
"That laundry is not clean," she said. "She doesn't know how to wash correctly. Perhaps she needs better laundry soap".
Her husband looked on, but remained silent. Every time the neighbour would hang laundry to dry, the young woman would make the same
comments.
About one month later, the woman was surprised to see nice clean wash on the line and said to her husband: "Look, she has learnt how to wash correctly. I wonder who taught her this!"
The husband replied: "I got up early this morning and cleaned our windows."
And so it is with life.
What we see when watching others depends on the purity of the window through which we look.
Easy to discuss other people, their lives and things that don't really concern us.
Yet we tend to forget- our window isn't that clean after all.
Clean up your window with the WORD! (THE TRUTH.)
LORD, please give us the strength, humility and courage that we may work on our faults first rather than seeing the faults in Others and castigating them.
Have a beautiful Week !
Read..This news is from warnewsupdates ....enjoy
NOW THE NEWS IN FULL.....
DoD Buzz: McCain: Ford-Class Overruns May Mean Fewer Supercarriers
The chairman of the Senate Armed Services Committee on Thursday blasted the U.S. Navy's Ford-class aircraft carrier program as an acquisition debacle.
Sen. John McCain, a Republican from Arizona who served as a naval aviator during Vietnam, didn't waste anytime launching into his criticism of the sea service's $40 billion effort to develop the first three new supercarriers.
"The Ford-class aircraft carrier program is one of our nation's most complex and most expensive defense acquisition projects," he said in his opening statement during a hearing on the matter. "It's also become, unfortunately, one of the most spectacular acquisition debacles in recent memory — and that's saying something."
WNU Editor: The debate on what role (and how many aircraft carriers does the U.S. need) is just beginning .... How many aircraft carriers does the US need? (Seth Cropsey and Bryan McGrath, The Hill). More here .... What Navy does America choose if the aircraft carrier is doomed? (George F. Will, new York Post)
Senators blast cost increases on U.S. Navy aircraft carrier -- Reuters
New Gerald R. Ford carrier class, as predicted, called $13 billion 'debacle' -- Stars and Stripes
Costly US Warship Reflects Pentagon Acquisition Dysfunction - McCain -- Sputnik
McCain Blasts Navy Carrier Procurement Program as a 'Debacle' -- Seapower
Why John McCain called this $13 billion aircraft carrier a "spectacular" debacle -- Washington Post
Ford aircraft carrier problems attributed to Pentagon 'culture' -- Daily Press
Senate raps cost jump for Gerald Ford aircraft carrier -- Detroit News
Document: GAO Report to Senate Armed Services Committee on Ford Aircraft Carrier Program -- USNI News
America's Premier, Next-Gen Carrier Just Got Demolished In New Report -- Daily Caller
KEEP SCROLLING TO THE END ...WE STILL GOT LOTS MORE .......
Source : http://www.coolnsmart.com/wise_quotes/
........

0 Response to "U.S. Senators Blast The Cost Overruns For America's Newest Aircraft Carrier"
Post a Comment